Overview of the project

The Cargill India Private Ltd. project in Wazirabad, Punjab, encompasses the construction of a mill tower, site grating, compound wall, and fencing. Key challenges included constructing a 450mm thick wall at a depth of 12 meters and prioritizing safety during deep excavation. The execution strategy involved open excavation with sandbag shoring, detailed excavation planning, and outsourcing soil removal. The project is progressing on schedule, with significant milestones achieved, particularly in wall construction and site grating. Effective management ensured successful navigation of challenges, prioritizing safety and adhering to timelines.

Client: Cargill India Pvt. Ltd.
Location: Wazirabad, Punjab
Duration: On going
Years of execution: 2024 - 2025
Scope included: Mill tower construction, site grating, compound wall, and fencing work.