HCCBPL Khurda Juice Line

This was one of the biggest milestone projects during the journey of VREP. The project was to build a Facility for a720-bpm hot fill juice line for the Hindustan Coca-Cola Beverages Pvt Ltd at Bhubaneshwar, Orissa.

Overview of the project

This was one of the biggest milestone projects during the journey of VREP. The project was to build a Facility for a720-bpm hot fill juice line for the Hindustan Coca-Cola Beverages Pvt Ltd at Bhubaneshwar, Orissa.
Completing the task on time with utmost safety was the biggest priority.

Client: Hindustan Coca Cola Beverages PVt Ltd.
Location: Khurda, Bhubaneshwar, Orissa.
Duration: 9 months.
Year of execution: 2016-2017.
Scope: Civil and Structural,Infrastructure (Roads etc).